StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Ye Canna Change The Laws Of Physics, MO PSC!

3/29/2019

1 Comment

 
What would you rather write about on a dreary Friday afternoon?  FERC's transmission incentives or the MO PSC Grain Belt Express Order?  Choices, choices.  Need coffee.

The MO PSC Order was bad.  Not so much in the decision they made, but in the way they tried to get there.  They could have just said "we like wind energy for political reasons" or "we approve this project because the company offered to sell service to Missouri municipalities at rates so low the project wouldn't be economic if those same rates were offered to all customers."  So much subjective reasoning, when objectivity was called for.  Therefore, here's a summary of the dumbest things written in the order.
The Missouri converter station will have bi-directional functionality, allowing Missouri utilities an additional means to earn revenue from off-system sales of up to 500 MW of excess power into the PJM energy markets.
This is one of the great lies about the environmental "benefits" for Missouri.  Presuming the power on the line when it gets to Missouri is "clean," 500 MW is offloaded for Missouri's use, then 500 MW of "dirty" coal power produced in Missouri is going to be loaded onto the line for the ultimate destination of PJM.  C'mon, I think P.T. Barnum had better lines!  This is virtual hogwash.  The same 500 MW of power that was fed into the line in Kansas (or wherever this thing terminates on the west end) will be offloaded in PJM, on the east end.  The only thing that happens in Missouri is that customers make payments.  The old dirty coal power will still be used in Missouri.  You can't segregate dirty and clean electrons on the grid.  Electricity is source neutral.  So how stupid would it be to divert 500 MW off the line and then divert 500 MW onto the line, when it's all the same 500 MW?  And if we want to talk about "environmental benefits" in Missouri, cranking up the coal plants to produce an additional 500 MW of excess power for sale to PJM only increases emissions in Missouri.  Sorry, GBE is going to do nothing to clear the air in Missouri. 
Picture
The HVDC technology of the Project is the most cost-effective and efficient way to move large amounts of electric power over long distances and can transfer significantly more power with lower line losses over longer distances than comparable AV lines.
What's an AV line?  And, btw, what's efficient or cost-effective about moving large amounts of power over long distances?  The cheapest, most reliable system is the one where source and sink are close.  See Scotty above.
The Project is a participant-funded, “shipper pays” transmission line. Grain Belt would recover its capital costs by entering into voluntary, market-driven contracts with entities that want to become transmission customers of the Project.
Picture
Under FERC requirements, Grain Belt must broadly solicit interest in the Project, the rates negotiated must be just and reasonable and without undue discrimination or preference, and the service must not impair regional reliability and operational efficiency.
FERC has specifically found Grain Belt’s process to select customers and allocate capacity to be “not unduly discriminatory”.
But that was before Grain Belt Express was purchased by a generation owner.  What approved procedures are in place to prevent self dealing by Invenergy, where it "negotiates" with itself to pay a price much lower than it negotiates with other customers?  Exactly none.  Trouble ahead...
The easement agreement limits the landowner’s legal rights and use of the easement property, including prohibiting any landowner activity that would interfere with Grain Belt’s use of the easement.
And this is one of the facts supporting approval in the public interest?
In 2021, MoPEP’s contract with Illinois Power Marketing Company providing 100 MW of coal energy and capacity to MoPEP will expire. MJMEUC’s agreements with Grain Belt and Iron Star would help MoPEP to replace the energy from Illinois Power Marketing Company with more affordable renewable energy.
Oh, so now in addition to changing the laws of physics, we're also instituting a time warp.  There's absolutely NO WAY GBE will be operational in 2021.  So I guess MoPEP is going to turn off the lights in 2021 and not turn them back on until GBE is in service?  Time to open a candle store, Missouri entrepreneurs!
The annual cost savings to MJMEUC member cities that participate in the Project will be dollar for dollar and will likely be passed through to their residential and industrial customers in the form of rate relief or invested in deferred maintenance to their electrical distribution systems.
Likely?  So you mean that MJMEUC members could actually use the "savings" for other things and the actual "public" customers may not see a dime of savings?
Grain Belt has a transmission service agreement with an Illinois load-serving entity called Realgy, which has agreed to buy 25 MW of transmission service for delivery to Missouri and 25 MW to PJM.
See what I mean?  The only thing Realgy is going to do is collect cash from the price differential between Kansas and PJM.  At least they're not pretending to offload "clean" power and upload "dirty" power.  This is all just one huge money making scheme.
Wal-Mart Stores, Inc. has established aggressive and significant renewable energy goals, including: (1) to be supplied 100 percent by renewable energy, and (2) by 2025, to be supplied by 50 percent renewable energy. Additionally, Wal-Mart Stores, Inc. has set a science-based target to reduce emissions in its operations by 18 percent by 2025 through the deployment of energy efficiency and consumption of renewable energy.
What?  (1) and (2) are conflicting goals.  Is it 100% or is it 50% by 2025?  Just stop shopping here.  This store is part of the problem.
Grain Belt currently has no employees.

Grain Belt has cash on hand, but not enough to complete either the development phase or construction of the Project.

Invenergy is not obligated to close on the Purchase Agreement unless (1) this Commission has approved the transaction proposed in the Purchase Agreement and has granted Grain Belt a certificate of convenience and necessity for the Project, and (2) the Kansas Corporation Commission has granted at least a 5 year extension of its certificate to Grain Belt and approved the change in ownership in the Purchase Agreement.

And this is the reason for granting a permit to Grain Belt Express?  Is this permit void if Kansas doesn't approve an extension?  I don't see that anywhere.
An interregional transmission line allows for low cost energy to be imported from a region with an excess of generation resources to a region with higher demand. The Grain Belt Project provides this benefit by moving wind power from Kansas (where there is an abundance of wind) into Missouri, MISO, and PJM, which will increase the supply of low- cost power in those markets.

Power prices in PJM are generally $10.00/MWh higher than prices that would be paid for the 500 MW of energy sold over the Project into the MISO market in Missouri. There is a very strong corporate demand for renewable energy in PJM, which contributes to Grain Belt being able to charge higher prices for that energy in PJM.

Where's the "demand" in PJM?  Grain Belt Express has no customers in PJM!
The wind industry will not need the federal production tax credit after 2023 because of continuing technology improvements.
Well, this is my personal favorite, bogus, unsupported statement in the whole Order.  It's footnoted to stuff Skelly said at hearing, which was nothing but his opinion and a whole bunch of malarkey.  Since when does Michael Skelly speak for the entire wind industry?  He hasn't worked in the wind industry in more than a decade.  And, obviously, his incorrect assumptions about the wind industry cost his investors $197M over the past decade.  Whoopsie!  The wind industry feeds off tax credits.  My opinion (just as good as Skelly's btw) is that once the tax credits sunset, the wind industry will blow out of town so fast it's going to make everyone's head spin.  When there's not a pot of taxpayer-financed gold to be had, the wind industry will no longer be interested in building wind.
The generation of electricity from wind energy results in no emissions, in contrast to traditional fossil fuel-fired generation. Grain Belt’s Project will provide an additional option for utilities to reduce their emissions of criteria air pollutants (e.g., sulfur dioxide), hazardous air pollutants (e.g., mercury), and carbon dioxide by purchasing cleaner renewable power for delivery on the transmission line in lieu of using existing or constructing new fossil fuel-fired generation assets.

The renewable energy delivered by the Project will reduce emissions in the Eastern Interconnection by displacing thermal generation, which emits sulfur dioxide, nitrogen oxides, and carbon dioxide, and will decrease water usage, all to the benefit Missouri’s environmental and public health.

Except when they fire up the coal plants to generate off system sales to PJM.  In fact, they may do more of that than using "clean" power from Kansas, since coal plants run when called and wind power runs when it wants to.  This is garbage.
The Project would have a substantial and favorable effect on the reliability of electric service in Missouri.
How so?  Did MISO order it for reliability purposes?  No?  Well then what use is additional "reliability" to a system that is already reliable?  And, really, how much reliability can be had from a transmission line that can only deliver 500 MW (while simultaneously exporting 500 MW from the same substation)?  HVDC is not compatible with AC, so there's only one possible interconnection.  Garbage, again.
Approximately $14.97 million in easement payments will be made in the first year of Project operation.
So, wait, you're telling me that easement payments to landowners won't occur until the first year of operation?  How many years could GBE be using people's land for free during construction before making any payments?  What if construction never gets completed, but land has been taken?  Does the landowner never get paid for what is taken from him?
Grain Belt developed the Missouri Landowner Protocol as part of its approach to right-of-way acquisition for the Project.
That's right!  The fox designed the security system for the hen house.  What protection is that to the chickens?
Grain Belt’s compensation package is superior to that of most utility companies.
I don't seem to remember any evidence of other utility company compensation packages being in the record.  What is this based on?  Someone's opinion again?
If Grain Belt obtains an easement from a landowner, the property will still belong to the landowner and can be utilized for activities such as farming, recreation, and other activities that do not interfere with the operation of the transmission line. After construction of the facilities, the landowner will retain the ability to continue agricultural production on the entirety of the easement area except for the relatively small footprint of the structures, which typically occupy less than 1% of the total easement area.
Except for that mega tower in the middle of the field that the farmer has to continually work around for eternity.  And except for anything Grain Belt says he can't do.  Seems more like Grain Belt would be in control of the ENTIRE easement, although the landowner would still pay taxes on it.
If Grain Belt and a landowner have reached agreement on the form of easement but are unable to reach agreement on the appropriate compensation, then at the landowner’s request, Grain Belt will submit the issue of landowner compensation to binding arbitration under Missouri law. The option of binding arbitration typically costs less, has more simplified procedures, and results in a final decision more quickly than circuit court litigation.
Quicker and costs less, you say?  Who would benefit from this?  Not the landowner.  Who pays for eminent domain suits?  Not the landowner.
Out of the 206 miles that the Project will traverse in Missouri, no more than nine acres of land would be taken out of agricultural production as a result of the structures installed for the Project in cultivated lands.
Who did your math here?  Certainly not a farmer.  I'd bet your math included merely the footprint of the towers, as if farming could occur right up to the structure without any safety margin.  This is just absurd.
Grain Belt has created the Missouri Agricultural Impact Mitigation Protocol, which establishes standards and policies to avoid, minimize, or mitigate any negative agricultural impacts that may result due to transmission line and converter facilities construction and operation.
Again, fox designing the security system for the hen house.  What does Grain Belt know about agriculture?  Does it fit in a thimble?
Grain Belt witness Richard J. Roddewig testified credibly that based on published research and Mr. Roddewig’s own research, transmission lines do not have a significant adverse impact on farmland prices and values.

The scientific weight of evidence does not support the conclusion that electric and magnetic fields cause any long-term adverse health effects, and the levels of electric and magnetic fields associated with the Project do not pose any known risk to human health.
And the scientific weight of evidence doesn't rule it out, either.  Both of these statements are industry propaganda.  Nobody in their right mind believes this.
Missouri courts have stated that for a company to qualify as a public utility, the company must be devoted to a public use for the general public. The evidence showed that when the Project is constructed and begins operation, it will transmit energy from wind farms in Kansas to wholesale customers in Missouri. In the case of MJMEUC, those customers are Missouri cities and towns that serve as electric providers to approximately 347,000 Missouri citizens. The hallmark of a public utility is the offering of utility service to the public without discrimination. Grain Belt will offer indiscriminate transmission service through an open access transmission tariff that will be filed and subject to the jurisdiction of FERC. While the Commission only has authority over facilities that are devoted to public use, an entity that constructs and operates a transmission line bringing electrical energy from electrical power generators to public utilities that serve consumers is a necessary and important link in the distribution of electricity and qualifies as a public utility. The Commission concludes that Grain Belt’s Project will serve the public use, and Grain Belt qualifies as a public utility.
Well, would you look at that?  The PSC has created new precedent!  If a private utility sells its product to a public entity, that automatically makes them a public utility?  I don't think so.  I don't think that is part of any existing precedent, so the PSC has nicely set this up for appeal like a set of bowling pins.  Great job!

I've long been of the opinion that regulatory decisions are not the product of careful evaluation of competing facts that lead to a conclusion.  Instead, it happens backwards, with the conclusion shaped by political factors, and then supported by a sifting of the evidence to find only the facts that support the previously reached conclusion.  This decision by the MO PSC is a prime example of this kind of political regulation.  How very disappointing.
1 Comment

Kansas Wants Invenergy To Put Up Or Shut Up

3/27/2019

6 Comments

 
That's the nice idiom.  There's also another appropriate here... use whichever floats your boat!

Yesterday was the deadline for the staff of the Kansas Corporation Commission to file their report and recommendation in the acquisition proceeding to transfer GBE to Invenergy.  While a lot of it was unsurprising dreck, there were a few gems in there, along with a few new recommended conditions.

First, a revelation:
Of the 1163 affected land tracts, GBE has made 582 written easement offers to Kansas
landowners but only secured signatures from 129. Because of the regulatory uncertainty
in other states, GBE stopped pursuing easement agreements in 2015 and eventually
released 122 of the signed agreements rather than pay the final balance due on the
easement agreements.

As noted earlier in my testimony, GBE has acquired easements from only seven of the
affected tracts of land. At one time it had 129 signed agreements but stopped actively
pursuing easements in 2015 and eventually released 122 of the easements.
Seven. 7.  Lucky number 7.  That's how many easements GBE owns in the entire state of Kansas.  Only 1,156 to go!

And why is this important?
What impact has the delay in acquiring easements had on the affected Kansas
landowners?

Because of the approved routing, I assume the landowners are aware the transmission line
will cross their property. But they have no indication of when or if it will occur, and they
have not been compensated for the easement across their property.

Would you expect the approved route to affect land values of the landowners?

In my opinion, the impact on land values is unknown. However, I believe knowledge of
the pending transmission line easement would need to be revealed in any land sales
transactions, which may affect a potential buyer's decision to purchase.

Has GBE kept in contact with the landowners to keep them apprised of it plans regarding the GBE Project?

As per the conditions in the 13-803 Docket, GBE is required to file quarterly updates with the Commission on it progress. However, all of those updates are filed confidentially with Staff and not available to the public or interveners in the 13-803 Docket. In the past, GBE has sent newsletters to those that have requested to be on a list to receive updates.  However, GBE...  *** Whoopsie!  Confidential Information  ***
GBE what?  Went belly up?  Was consumed by its own hubris?  Not sure why this is confidential...  anyhow...
The only benefit that can be attributed to the landowners affected by the approved route
of the GBE Project would be the certainty of the line's impact on their property and
compensation for the line easements. In this case, certainty can be provided by the sunset
provision dismissing the approved route, or by GBE or its successor completing the purchase of the necessary easements through Kansas.
So the staff recommended this condition to approval of the acquisition:
If the Commission approves the acquisition and agrees to extend the sunset provision in the 13-803 Docket, I recommend the Commission require Invenergy to make
preliminary payments or acquire the easements necessary to construct the Kansas portion of the GBE project regardless of its success in resolving its regulatory issues in the other affected states.

Invenergy shall make preliminary easement payments to all Kansas landowners affected
by the line siting within 12 months of a decision to extend the line siting sunset provision found in Docket 13-GBEE-803-MIS (13-803). If the sunset extension is not approved and Invenergy requests approval of a new line siting route, Staff recommends the Commission require Invenergy to make preliminary easement payments within 12 months of gaining approval for a new line siting.
Dr. Freud, paging Dr. Freud...  new line siting route?  Where did this come from?  Why would staff bring that up and include it as a condition for approval?  If we're just talking about possibilities here, why not include one about a meteor falling from the sky and crushing Invenergy's Chicago headquarters, what would Invenergy have to pay Kansas landowners in that instance?  So... a re-route is a remarkable possibility.  In fact, it looks like it may be a distinct possibility.

And now that we're over the Freudian portion of my comment...  Invenergy is going to have to shell out a lot of money within one year of approval.  If it later decides not to go forward with the project, it's not getting any of its money back.  And only one year to acquire 1,156 easements and make initial payments... while the uncertainty of approvals in other states still hangs in the balance.  This is impossible.

Put up or shut up, Invenergy.

This staff person also recommends, "When the GBE Project and/or AC Collector System become operational, Invenergy will maintain sufficient personnel in the region of the facilities such that it can provide adequate emergency response to any portion of its Kansas operations within one hour of being notified of an emergency."

Looks like there's going to be lots of little Invenergy offices across Kansas, with a skeleton staff sitting around waiting for an emergency to occur.  Well, at least that will guarantee a handful of permanent jobs.

However, this is only a staff person's recommendation.  What the Commissioners will eventually do is anyone's guess.

My guess is that Invenergy is screaming and having a big ol' tantrum today.

Too bad Missouri doesn't care for its landowners this way.  How bad do you have to be for Kansas to look good?  At least someone seems to be looking out here...
6 Comments

"It is a tale told by an idiot..."

3/22/2019

0 Comments

 
Building into this week's Grain Belt Express fantasy are the off-base comments of potential new owner Invenergy.  The company was slow getting off the blocks, even though it probably had the inside skinny on the pending approval.  In the wake of the decision, there was a resounding silence from Invenergy, which created a media void that others stepped right into.  This shaped a news stream laced with healthy amounts of skepticism.  It just didn't work out that the PSC's press release adequately filled the void of silence from Invenergy.

When pressed for comment, Invenergy responded with a bunch of glittering generalities and inconsequential trifle, like this:
“Invenergy is grateful for the thoughtful and thorough consideration given to the Grain Belt Express transmission project by the Missouri Public Service Commission and we are pleased with the Order granting Grain Belt Express a Certificate of Convenience and Necessity,” Conley said Thursday.
Invenergy spokeswoman Beth Conley praised the PSC’s action and said Invenergy put the project on solid financial ground.

“The order confirms that the Grain Belt Express project is in the public interest and is good for Missouri,” Conley said. “Invenergy looks forward to the next step in the regulatory process before the PSC and to bringing low-cost power, quality jobs and new tax revenue to Missouri.”
“The Grain Belt Express is important because it is a transformative infrastructure project that will provide access to more low-cost renewable power to American consumers and communities,” Conley said.
“Today’s order confirms that the Grain Belt Express project is in the public interest and is good for the state, and a good project is made stronger by Invenergy’s participation and we’re excited for what this means,” Conley said.
"The Order confirms that the Grain Belt Express project is in the public interest and is good for Missouri. The Grain Belt Express project is made stronger through Invenergy’s participation because of our strong record of project execution, strong financial position, community partnerships, and landowner relationships," company spokeswoman Beth Conley said in a statement.
As Shakespeare's Macbeth said, "It is a tale told by an idiot, full of sound and fury signifying nothing."

But what about Illinios, Invenergy?  You're not doing anything in Missouri without an approved route in Illinois, right?  I mean, what would be the point of building the project in Missouri if there wasn't a clear, connecting path through Illinois that enabled Invenergy to reach the PJM Pot 'O Gold?
The company is now focused on the separate regulatory matter of having its acquisition of the project approved in Missouri and Kansas, said Beth Conley, an Invenergy spokesperson.

Though Missouri had long been the only holdout among the four states on the project’s path, another hurdle arose last year in Illinois, which rescinded its approval on the technicality that Clean Line did not have a physical presence in the state and therefore could not qualify as a utility. Conley said there was still “no existing regulatory approval in Illinois” and “nothing pending,” as well.
Grain Belt Express also no longer has the OK to be built in Illinois after a state appeals court last year reversed the approval of the Illinois Commerce Commission. Conley said Thursday that “there is no pending regulatory case for the project in Illinois.”
Clean Line had been working on the proposed direct-current power line since 2010 and had said last year that it still hoped to bring the project online by 2023 or 2024.

Invenergy spokeswoman Beth Conley said that timeline has not been changed by the proposed sale of the project. The power line would be the largest transmission project undertaken by Invenergy.
2023?  Isn't that a little optimistic for a company that still needs regulatory approval in Illinois?  It took Clean Line's Rock Island project several years to get through permitting in Illinois, only to have its permit snatched away by the courts a couple years later.  And that's not counting the appeal to the Illinois Supreme Court, which added another couple years.  So we're talking 6 years, just for clear regulatory approval in Illinois, if things go swell (which they won't).  Even if Invenergy filed an application in Illinois today, it would be 2025 before it could possibly work its way through the Illinois system.  How long would the project take to build, once it had approvals?  2 to 3 years.  We're getting a lot closer to 2030 than we are to 2023.  Beth's timeline isn't realistic, nor even logical.  It sounds more like a costume for a farce, a scene in an improbable drama.  But it really tells the public nothing about what's about to happen next.

Instead, Invenergy wants the media to focus on other fairy tales, such as this:
Invenergy has experience building similar projects globally, and spokesperson Beth Conley said that background will help navigate challenges with residents.

“Invenergy has built more than 140 sustainable-energy projects around the world, and we’ve done that by really executing on our reputation as being a company that is committed to the communities that host our projects,” Conley said.
Conley, the Invenergy spokeswoman, said the company has established good relationships with landowners and community leaders in building its more than 146 worldwide projects and the company will bring “that same level of dedication” to stakeholders in the Grain Belt project.
Similar projects?  What's "similar" to a 780-mile merchant transmission line with eminent domain authority?  Not the short, private generation tie lines Invenergy builds through voluntary agreements with landowners.  Not gigantic wind farms and other generation plants that lease land from willing landowners.  Invenergy has ABSOLUTELY NO EXPERIENCE building and operating a merchant transmission line of this magnitude with negotiated rate authority using eminent domain.

Invenergy has no background using eminent domain to acquire land.  Negotiating voluntary agreements with absentee landowners who like the large cash royalties that come with wind leases is about as far as you can get from negotiating a transmission line easement under threat of eminent domain with a hostile landowner who sees no value in low, one-time payments or cheesy yearly pittance payments for a perpetually burdensome easement.  I'm afraid Invenergy's "experience" is of little use in this situation and could actually become detrimental if they become inebriated at the fountain of power fueled by eminent domain authority.

And as far as those landowner relationships Conley brags about?  I think there's more to be revealed by the way Invenergy is hated by numerous communities it has invaded.

Such as Rhode Island.

Wisconsin.

Minnesota.

Oklahoma.

Colorado.

Kansas.

Indiana.

New York.

Oklahoma, again.

California.

Pennsylvania.

South Dakota.

Iowa.
Need I go on?  In state after state, citizens oppose Invenergy projects planned for their communities.  The stories are chock full of accusations of public official bribery, lawsuits against local government, detrimental health effects, property devaluation, and pitting neighbor against neighbor which causes community upheaval. 

The real story is told by what is not said by Invenergy spokespersons.  I've got my
on you, Invenergy.
0 Comments

Debate About Grain Belt Express Is Alive and Well

3/21/2019

2 Comments

 
The Missouri PSC issued an order granting a CCN to Grain Belt Express yesterday.  What does that mean for the viability of the project?  In the grand scheme of things... not much.  Grain Belt Express, as presented to the MO PSC as a 780-mile transmission line from southwestern Kansas to Indiana, is still never going to happen, IMO.  The reasons are myriad, and hopefully I'll get to most of them over time.  More garbage has been generated than fits in one trash truck, ya know.

Let's start here.  Permitting whack-a-mole.  This is an old one, but still very much appropriate.  Grain Belt Express just can't whack all the moles and win this game.  The biggest, baddest mole standing in its currently proposed way is Illinois.  Based on prior court decisions in that state, GBE just can't be permitted.  Pretending it can is unrealistic.  Is GBE lying to us, or is it lying to itself?

And then there's the ridiculous garbage the PSC generated yesterday.  We'll get to the actual Order later.  First, let's look at the press release the PSC issued.

The PSC is a regulator, not a politician, not a public relations agency.  It's supposed to deal in facts.  Its decisions are legal opinions.  It should not have to "sell" them to the public.
Mission Statement
We will:
  • ensure that Missourians receive safe and reliable utility services at just, reasonable and affordable rates;
  • support economic development through either traditional rate of return regulation or competition, as required by law;
  • establish standards so that competition will maintain or improve the quality of services provided to Missourians;
  • provide the public the information they need to make educated utility choices;
  • provide an efficient regulatory process that is responsive to all parties, and perform our duties ethically and professionally.
You failed, MO PSC.  Any respect I used to have for the MO PSC is now gone.  No, it's not that they issued a decision I don't agree with.  That happens a lot from all kinds of regulators.  It's the way they went about it.  Even a regulatory decision you don't agree with contains facts and logic, sometimes a bit of opinion, but there's usually a sufficient amount of legal reasoning that forms a platform upon which the decision was made.  You may not agree with the decision, but you can clearly see how it was created.  The MO PSC's decision happened inside a black box.  And it reeks of politics.

First thing to come out of the box is the press release.
The Commission granted a CCN to Grain Belt determining: 1) there is a need for the service; 2) Grain Belt is qualified to provide the proposed service; 3) Grain Belt has the financial ability to provide the proposed service; 4) Grain Belt’s proposal is economically feasible; and 5) the service promotes the public interest.
The Commission says it issued a CCN to Grain Belt, but it really issued one to Invenergy.  Invenergy has the financial ability and is qualified to provide the service -- Grain Belt has no employees and no money.  Neither Grain Belt nor Invenergy has a proposal that is economically feasible.  There's only 2 customers, one of which was documented to be paying below cost rates.  These customers cannot financially support the proposal.  There are no other customers.  Potential customers don't pay the bills.  Supplying below cost service to one customer is Missouri does not promote the interests of the entire public.
The Commission stated the evidence in the case demonstrated that the Grain Belt project will create both short-term and long-term benefits to ratepayers and citizens of the state. In addition, the project would have a substantial and favorable effect on the reliability of electric service in Missouri.
Benefits to citizens?  Where?  What citizens?  What benefits?  This statement is created out of thin air.  As far as "reliability" goes... a transmission line contracted to serve only select customers with unreliable wind power is not "reliable."  Wind cannot be called to produce when needed.  It's not an open access transmission line that will serve all customers equally, and Missouri may only receive 500 MW, although contracted amounts are much, much less.  This is not a "reliability" transmission asset.  It's a private driveway for select customers to receive special, supplemental wind power so they can pretend to be clean and green and all sorts of peripheral things.  As if electrons can be segregated by color.
There can be no debate that our energy future will require more diversity in energy resources, particularly renewable resources,” said the Commission. “We are witnessing a worldwide, long-term and comprehensive movement towards renewable energy in general and wind energy specifically. Wind energy provides great promise as a source for affordable, reliable, safe and environmentally-friendly energy. The Grain Belt Project will facilitate this movement in Missouri, will thereby benefit Missouri citizens, and is, therefore, in the public interest.”
Whaddya mean there can be no debate?  Of course there's debate.  There's a HUGE debate going on in this country and around the globe.  Wind energy is not the solution to our energy woes.  It's just a gluttonous industry that has been greenwashing America for years, and stuffing its pockets with our tax dollars.  It's not affordable, it's not sustainable.  It's not safe for the people who have to live around its generation plants.  And it's certainly not reliable.  Wind is not a baseload source of power.  It cannot be controlled to ramp up and down to meet need.  Wind does what it wants, and those who depend upon it for a source of electricity are the ones whose electric use ramps up and down to follow the wind.  Who wrote this garbage?  Was it the wind industry?
The Commission noted that any negative impacts of the project on the land and landowners will be mitigated by: 1) a landowner protocol to protect landowners; 2) superior compensation payments; 3) a binding arbitration option for easement negotiations; 4) a decommissioning fund-a fund for this type of project would be the first of its kind in the country; and 5) an agricultural impact mitigation protocol to avoid or minimize negative agricultural impacts. Agricultural impacts will also be reduced because no more than nine acres of land in Missouri will be taken out of agricultural production as a result of project structures, and the proposed route does not directly impact the operation of any existing center pivot irrigation systems.

“Many of the landowners’ concerns will be addressed through carefully considered conditions placed on the CCN,” said the Commission.
Landowner concerns have NOT been addressed.  Landowners are still extremely concerned.  The PSC's conditions did nothing to ameliorate them.  The "landowner protocol" and "agricultural impact mitigation protocol" were created by Grain Belt, not the landowners, therefore landowners concerns are not addressed.  These documents address only the company's concerns.  Landowners were not consulted in the creation of these documents.  It's nothing more than the fox designing a security system for the hen house.  It's worthless and does nothing to satisfy landowners.  The decommissioning fund is also so much nonsense.  It has no substance, no rules, and is completely unworkable.  It's just more glittering make believe.

Superior compensation payments?  Superior to what?  Receiving nothing?  Since the PSC's land is not subject to eminent domain, and the PSC has never been subject to condemnation and eminent domain taking, it's opinion that the compensation payments are "superior" is just so much hubris.  In fact, it's completely insulting to landowners.  It's disrespectful.

And speaking of disrespectful, here's the pinnacle of propaganda:  only 9 acres of land will be taken out of agricultural production.  Just 9 acres!  Across 206 miles of 200-foot wide linear right of way.  The PSC has deemed every square inch of the proposed right of way to be agriculturally workable right up to the base of the tower.  I guess none of these folks have ever tried to drive a huge piece of farm equipment right up to a transmission line pole.  And they've never had to fly around a transmission pole to apply pesticide or fertilizer.  And they've never had to try to grow something along a strip of land that no longer has top soil.  And they're certainly not going to accept liability for any farmer who tries to farm right up to the base of the transmission tower and has an accident.  This is absolutely absurd.  And, ya know, it's something Hans Detweiler used to tell farmers in Illinois... that only 12 acres of land would be taken out of use for the entire Rock Island Clean Line project.

Gotta wonder, who wrote that stunningly bad press release?  I hope that person's food and farm goods will be supplied solely by that compromised 9 acres in the future.

We're only getting warmed up here... more to come...
2 Comments

Landowners Vow To Appeal Grain Belt Express Decision

3/20/2019

0 Comments

 
Two landowner groups in the bull’s-eye of the recently approved Grain Belt Express (GBE) high voltage electric transmission line say their fight will continue.  The Missouri Landowners Alliance (MLA) and Eastern Missouri Landowners Alliance (EMLA), whose membership encompasses the entirety of GBE’s 200-mile route across Missouri, have decided to appeal the decision of the Public Service Commission to the Missouri Court of Appeals.  The groups say that GBE is not a public utility under Missouri law, and as such does not possess the solemn power of eminent domain to take land for its line.
 
"A public utility has the obligation to serve everyone within its service territory, and to charge the same rate to all similarly situated customers.  On the other hand, as a non-public utility, Grain Belt has the right to negotiate the best deal it can get with individual utility and other customers, and to negotiate with those who are most likely to pay it the highest price and different prices for the same service.  This is discriminatory and does not meet public utility requirements under Missouri law,” said Phil Brown, an attorney with EMLA.
 
GBE’s own studies show that Missouri already has excess generating reserves.  And GBE would not help any utility in the state to meet Missouri’s renewable energy requirements.  GBE could slow down the development of renewable energy resources in Missouri by replacing them with imported renewables from other states.  Landowners also point out that GBE has yet to attract commercial interest. No investor-owned utility or rural electric co-op has signed on with Grain Belt.  Without customers paying sustainable rates, GBE is not economically feasible and cannot be built.
 
The battle now also shifts to counties crossed by GBE, who have authority under state law to deny GBE from crossing the counties.
 
Wiley Hibbard, Presiding Commissioner of Ralls County said, “Ralls County has put a hold on granting assents until the development of our 229.100 application process is complete.  Knowing that the commissioners of each county have the most thorough knowledge and understanding of how these projects will affect their counties, the Missouri Association of Counties (CCAM) has again passed a resolution advising members of the Missouri Legislature to protect and preserve Mo Rev. Statue 229.100.”
 
The Missouri legislature is also taking action on GBE.  Rep. James Hansen has introduced legislation, House Bill 1062, to prevent the use of eminent domain by non-public utilities.
 
“I remain committed to Missourians in ensuring that eminent domain is not used by non-public utilities for profit,” said Rep. Jim Hansen.  “I have introduced legislation that will close this gap in existing law and will work expeditiously to shepherd it through the legislature,” he continued.
 
The project still faces many hurdles before it can be built.  The Missouri PSC is investigating whether to approve the sale of the project to Chicago-based Invenergy.  Kansas officials are engaged in a similar process.  The cases are not expected to be resolved until mid-summer, or later.
 
GBE must also re-apply for a permit to cross Illinois, after having an earlier permit revoked by an Illinois appeals court, which ruled that GBE was not a public utility under state jurisdiction.
 
“Given the uncertainty of the project in Illinois, we wonder if Invenergy actually intends to build this project across Kansas, Missouri and Illinois to a connection point in Indiana that ties into lines that serve east coast states,” Jennifer Gatrel, spokeswoman for Block GBE-Missouri.  “Invenergy has been very mysterious about its intention.”
 
“We urge landowners and opponents of GBE to circle the wagons and gain strength from each other during this period of uncertainty,” said Russ Pisciotta, president of Block GBE, a statewide organization of opponents of GBE. 
 
Pisciotta said they are working on an information packet for landowners that aims to provide some guidance on possible future steps, as well as a review of landowner rights under the law on GBE wanting to take their land.  Landowners who do not receive a packet are urged to contact Missouri Landowners Alliance, Block GBE, or Eastern Missouri Landowners Alliance.
 
“This is far from over,” said Marilyn O’Bannon, spokeswoman for EMLA.  “This battle is young yet.  Anything can happen.  Landowners are urged to exercise great caution when interacting with GBE’s representatives.”
 
MLA and EMLA recommend that landowners not sign any document related to an easement on their property without first reviewing it carefully, preferably with advice from an attorney. 
0 Comments

Signals of Subterfuge?

3/1/2019

1 Comment

 
Missouri regulators signal readiness to OK Grain Belt Express transmission project

Does that look anything like this?
"Signal" is today's popular, but sadly overused and misused, journalistic punt.  It drives me nuts to see all this "signaling" going on, and any journalist who thinks they are clever or original by using it is actually just a lazy imitator.  Please remove this idiotic word from your stories. 

Now that I'm over the headline, what "news" does this story give us?  Couple of things, well beyond what a thinking public might surmise about possible conspiracy within the Missouri government.

First, there's this:
Invenergy has told the Missouri PSC that it plans to begin construction in 2020 and complete the project in four years.
That's right, it did.  It also told the PSC at hearing that it would begin eminent domain proceedings against 700 landowners immediately after receiving any permit from the PSC.  The witnesses' reasoning was that it must quickly begin surveying and core drilling to finish engineering of the line and landowners would not willingly give permission for that work.  Company mouthpiece Hans Detweiler told the PSC that the only remedy for uncooperative landowners was to take the right of way using eminent domain so it wouldn't need permission to enter for testing.

Hans, you dope!   Maybe you actually believe that (in which case you're demonstrating how very little you know about actually building transmission), but real transmission companies never do that.  Under most state laws, an entity with eminent domain authority has the right to enter property to perform testing prior to initiating a take.  AEP has been using this bully tactic recently, filing for court orders preventing landowners from interfering with entry and testing.  Except the landowners were not interfering in the first place.  The landowners simply refused to grant permission voluntarily and sign company release forms.  A court cannot force a landowner to sign a permission form.  It can only order the landowner not to interfere (something they were not doing in the first place).  The transmission company may risk getting on the wrong side of a local judge, but they'd probably get worse by pretending a take was necessary to perform simple surveys.

Does Invenergy have money to burn?  Why would it be spending bundles acquiring property and testing it to microsite a route when it doesn't have permits in all four states?  Until all permitting and siting is completed at the regulatory level, Invenergy would only be guessing and hoping the money it spent in Missouri would allow a route that would be contiguous with unapproved routes in other states.  And even within Missouri, Invenergy does not have a converter station site.  The option it had in Ralls County has expired and the landowner did not renew it.  As well, Invenergy does not have an approved interconnection in Missouri where it can tie into the existing transmission system operated by the Midcontinent Independent System Operator.  In fact, Invenergy isn't even in MISO's queue for study of a proposed interconnection.  Therefore, any final routing through Missouri would simply be a very expensive guess at this point... unless Invenergy doesn't plan to connect in Missouri at all and simply pay off MJMEUC and deliver nothing at all.

Is the Missouri Public Service Commission this gullible?  After nine years of Clean Line baloney before the Commission, are we supposed to believe they don't smell anything at all suspicious?  I don't believe it.  Not for a second.  I wonder what the MO PSC, elected officials, and government agencies know that they're not saying?

There's simply no way GBE will begin construction next year.  No way at all.

GBE does not have a permit in Kansas.  GBE does not have a permit in Illinois (and even if it applied today, it would be years and years before any decision would be made).  Essentially, GBE has done nothing to support a connection to PJM, and nothing to support a connection to MISO in Missouri.  GBE is an empty extension cord that doesn't connect to anything.  Who spends money building that?

And then there's this:
A company spokeswoman didn’t respond to an email seeking comment.
Right.  A company ready to begin construction on a transmission project it's been trying to permit for years receives "signals" that approval is imminent, and it has no comment.  Invenergy has failed to say much of anything in the media lately, and has refused to share any future plans.  Is it because Invenergy's REAL plan may signal something that Missouri can't permit?  There's more here than meets the eye and the only signals being emitted are a bunch of obscuring smoke.

No matter.  There's still this:
In the meantime, a landowner group says it’s not giving up its fight to block the transmission line.

“We remain committed to defending property rights,” said Jennifer Gatrel, a spokeswoman for Block Grain Belt Express.

Gatrel said there’s strong local government opposition to the project along the planned route and she believes many of the eight county commissions will refuse to sign off on needed assents allowing construction.

So, what do all these "signals" indicate?  Nothing new.  Grain Belt Express is still impossible.  Landowners are not backing down and won't be intimidated by new owner Invenergy.

This isn't over yet.  Carry on.
1 Comment

American Electric Power Destroys Farmer's Land While He Attends Hearing To Save It

2/22/2019

1 Comment

 
How low will you go, AEP?  While farmers opposing its unneeded, uneconomic Transource transmission line were attending the first day of the Pennsylvania PUC administrative hearings to decide whether or not to permit the project, AEP sent its out-of-state contractors in for a joyride across their land.  And this is the destruction they came home to yesterday...
And Transource agents lied, flat out lied, to the landowner and told him they would be out on a different day.  This is no coincidence.  Transource did its trespassing and destruction with full knowledge that the landowner would be elsewhere, trying to protect his property from exactly this.

How in the world can anyone (especially regulators) believe all this company's promises about taking care of the land it disturbs and paying for damages when this is what happens when simple core drilling to examine tower sites is done? 

This is the reason a utility should never be permitted to trespass on private property before its project has been approved by regulators and it has a permit in hand.  The destruction and safety issues will continue and get much worse.  And for what?  So ratepayers in Washington, DC can save 20 cents on their electric bill?  This project will never be approved.  American Electric Power lies to landowners and wantonly destroys their property.  This isn't a company you'd want as a tenant on your land in perpetuity.

And one more thing... here's the landowners showing up at the PA PUC hearing yesterday in a rented school bus that they paid for.
Picture
And here's Transource, its high-priced lawyers, and AEP corporate stuffed suits arriving at the same hearing like movie stars in a Mercedes limo.  I'm surprised there wasn't a red carpet, although maybe the driver just hadn't unfurled it yet.  Who paid for that?  I did.  You did.  Struggling electric consumers in numerous states paid for these clowns to ride in style.
Picture
This travesty simply has to end.  We can't afford it.

Shame on you, American Electric Power!
1 Comment

Buzzwords, Bluster, and Baloney:  Stirring Up Grain Belt Express

2/18/2019

1 Comment

 
Picture
Languished, obstacle, move forward, favorable, finish line, ambitious, momentum, demand, key, tax credit, renewable, next steps... what do these words have in common?  They're tired buzzwords used to describe tired transmission ideas to a tired public who has stopped caring.  Ya know, if it wasn't for the St. Louis Dispatch energy reporter's own personal greenwashed beliefs, there wouldn't be a "story" here.

What's wrong with this article?  It's misinformed, propaganda-driven malarkey that relies on glittering generalities  and opinion.  It's not "news."  It belongs on the Editorial page, not in "business news."
The proposed multistate transmission line, Grain Belt Express, has languished before Missouri regulators for years — with their at times controversial rejections representing the last major obstacle to sending Kansas wind energy east along an intended 780-mile path.
A bigger obstacle to sending Kansas wind energy east is Illinois.  It seems like the reporter is completely oblivious to the court decision in Illinois that vacated the Grain Belt Express permit in that state.  GBE is back to start in Illinois and it is highly unlikely that it will ever be permitted.  The Illinois Supreme Court has serious concerns that Clean Line's merchant, negotiated rates business model does not meet the definition of a public utility.  If it's not a public utility, it doesn't need a permit from the Illinois Commerce Commission.  Clean Line is free to build any transmission it wants in the state, but it may not use a public utility's eminent domain authority to do so.  The same concern has been briefed in Missouri.  Grain Belt Express will not serve all customers equally, which is a hallmark of public utility status.  Without all of the requisite qualifications, Grain Belt Express cannot be a public utility.
While the overall decision on the project’s approval remains the bigger matter before the PSC, the regulatory body announced this month that it was also warming up to begin the separate process of approving its sale.
Warming up?  What the heck does that mean in a regulatory context?  GBE and Invenergy have applied for Commission approval of the sale.  The PSC has set a hearing to determine a procedural schedule.  It does not imply approval.  It merely illustrates the timing differences here where the companies want the PSC to issue a permit to a project based on new ownership BEFORE it has approved said ownership.  It bolsters the argument of Missouri Landowner Alliance that the PSC cannot approve the project based on the qualifications of Invenergy because Invenergy does not yet own the project.
Some outside experts in Missouri speculate that Invenergy’s bid to take over the project can only help its odds of getting across the finish line.
Outside experts?  Renew Missouri is a party to the PSC case.  Invenergy is the applicant.  These are INSIDERS.  And there is no "expertise" here.  It's talking heads spewing glittering generalities and misinformed, self-serving opinion.

James Owen:  this guy has shot himself in the foot so many times by spewing falsehoods in the media that nobody even listens anymore.  If Invenergy wants to buy the project that's proof there's value to the project?  The only proof there is that Invenergy has some sort of scheme in the works to leverage some parts of the project to serve its quest for profit.  The Invenergy/GBE deal is contingent upon successful permitting in Kansas and Missouri.  It is not contingent upon successful permitting in Illinois and Indiana, nor successful transfer of GBE's FERC negotiated rate authority to proposed new parent Invenergy.  If Invenergy intended to build GBE as currently proposed, all those conditions would be present in the contract.  They're not, therefore Invenergy does  not need Illinois or Indiana permits, nor negotiated rate authority, for whatever scheme it may cook up with the carcass of GBE.
She declined, however, to give updates or estimates about Invenergy’s anticipated, or hopeful, timeline for the project.
“I think it’s premature for us to be talking about timelines right now,” said Conley. “When we have a decision in that case (from the PSC), then we can really consider timelines and development and what the next steps for the project are.”

Is that right, Beth?  You can't reveal Invenergy's actual plan for GBE until after the PSC approves the wolf in sheep's clothing?  Then why was it that two Invenergy witnesses told the PSC at hearing last December that the company would have to begin eminent domain proceedings against 700 landowners immediately after approval, and well before it had all state permits in place to build the original concept?  Invenergy admitted that there have been discussions about ending the project in Missouri, or taking a different route around Illinois.  Invenergy doesn't intend to build Grain Belt Express all the way to Indiana and then sell capacity through negotiated rates, does it?  The only thing "premature" here would be letting Invenergy's cat out of its bag and demonstrating its true intentions to the MO PSC before it makes a decision on the project. It's a lot easier to beg forgiveness than seek permission, isn't it, Invenergy?
The project would be accompanied by the large-scale construction of new wind energy generation in western Kansas. Although about 85 percent of electricity distributed by the project would be destined for other states, it would power approximately 200,000 Missouri households. The PSC, even in denying the project through certain legal interpretations, has agreed that it is in the public interest, and would save Missouri customers millions of dollars by promoting access to cheap wind energy.
This is the reporter's opinion.  There are no facts here.  Building a transmission line does not ensure construction of any generation in any specific location.  Eight-five percent will not be destined for other states.  If GBE would have a capacity of 4,000 MW, then 15% would be 600 MW.  GBE proposes 500 MW for Missouri, if it can find customers for that much.  Instead, it only has purported customers for up to 200 MW, which is 5%.  And of that 200 MW, only a bit over 100 MW has actually been "sold" to municipalities in Missouri.  And where does the 200,000 households come from?  Did the reporter add up all the participating municipalities to get that figure, or did he just harvest it from some GBE propaganda?  So, more than 95% is destined for other states currently.  And of that 95%, only 50 MW, or just over 1%, has been tentatively sold.  And since a merchant project cannot be built without customers (customers who would pay much higher rates than those loss leader rates offered to Missouri municipalities), any prognostication about who would buy the capacity and where they would be located is pure speculation and fairy tale.  Also, it matters not what the MO PSC did on an entirely different matter.  GBE has changed significantly since its prior application, and the PSC's opinion may have changed significantly as well.
Picture
The transmission project would be the biggest, by far, that the Chicago-based company has ever undertaken. The company has developed more than 400 miles of combined transmission lines in its history, Conley said — just over half of the distance that Grain Belt would cover.
But what kind of transmission lines has Invenergy developed, Beth?  They've all been short generation tie line segments built without eminent domain authority.  This is a comparison between apples and oranges.  Invenergy has no experience with open access transmission lines with negotiated rates using eminent domain authority.  All Invenergy's transmission lines are private use for the company to sell its product.  Are we supposed to infer that GBE would just be another one of those, albeit more than 700 miles long?  Great!  But no eminent domain authority would be appropriate for that kind of project.  And besides, Invenergy has not applied to build any transmission project.  The PSC cannot approve this project as something Invenergy is building because Invenergy does not own it.
But for any prospective wind energy developer, the end of 2020 has long been a key point on the calendar.
After that point, production tax credits for completed wind projects begin to phase out. Even without receiving the full tax in their entirety, Clean Line officials previously said they felt the project would be cost-effective, thanks to technology and declining costs. Invenergy shares that belief, Conley said — full tax credits or not.
Does this reporter not know that Clean Line isn't eligible for, and will not receive, any tax credits?  There are no tax credits for transmission lines, and GBE cannot be built in time for any new wind to be built that qualifies for the credit.  It sounds good, but it's pure fiction, certainly not "news."

Perhaps this reporter should have attempted a balanced piece by talking with opponents to the project?  It's almost as if there is no opposition at all.  Failure to recognize the opposition does not make it disappear.  It only makes this article look biased.  And what's up with that graphic?  It shows three Clean Line projects, two of which have been officially cancelled, without any recognition whatsoever by the reporter.

This article is opinionated garbage.  The St. Louis Post-Dispatch needs to do better.
1 Comment

Unapproved Transource Invades Private Property

2/11/2019

1 Comment

 
The Transource Independence Energy Connection is still in the regulatory process and has not been approved by Pennsylvania, nor Maryland.  In fact, Transource is barely limping along at state regulatory commissions and I'm pretty certain it will not be approved.

However, Transource is in a big hurry to spend money on its project that will have to be reimbursed by all electric customers in the region.  With a guarantee granted by the Federal Energy Regulatory Commission, Transource can apply to have all its prudent costs reimbursed by electric consumers, plus 10.4% interest, in the likelihood that the project is eventually abandoned and never built.  Transource is all about spending as much as possible as quickly as possible.

Today, Transource's Texas-based construction company entered private property under court order to drill giant holes for soil samples.  The idea is to investigate the possibility of erecting a 130-ft. tall transmission tower right there, in the middle of this cornfield.
Picture
Transource asked landowners for permission to enter their properties to do testing, cut vegetation, and do core drilling.  Landowners refused to grant permission voluntarily.  Transource took landowners to court to get an order permitting them to enter private property to do this preliminary work.  Testing and surveying has taken place without landowner permission.  And now the drilling starts.  Construction workers have entered private property with their tracked drilling rig and vehicles (and from the looks of it, made a mess in the process) and gone about their business, under police guard no less.

But not without notice.  Not without protest.  Today, dozens of landowners showed up at the Transource drilling site on very short notice, and in bad weather to boot, to stage a peaceful protest to this unwarranted destruction of their community.  It looked like this.
How alarming is it that these landowners are being invaded by an out-of-state company, having their fields disturbed and damaged, without receiving any compensation for their trouble?  And for an electric transmission project that is not approved and most likely will never be built.

To stand with these landowners and to get more information, including live video of today's protest, visit them on Facebook at Citizens to STOP Transource - York.

These landowners are not giving up and not giving in, but will resist Transource at every juncture.  Bravo!
1 Comment

More Governor Letters in Missouri

2/1/2019

0 Comments

 
Dear Governor Parson:
 
As a farmer and a Commodity Trader for one of the largest Grain Companies in Missouri and the world, I am writing today in opposition of Grain Belt Express as the proposed route will be crossing my family’s University of Missouri Extension Century Farm in Monroe County.  I am adamantly opposed to a private for-profit company applying to Missouri Public Service Commission for a Convenience and Necessity Certificate that if approved would give the authority of Eminent Domain.
 
On the coldest days of February 2015, our Missouri utility companies were selling excess power to PJM grid and making over million dollars a day.  That money was coming back to Missouri utility companies, workers and citizens as the cooperatives could pass along profits (patronage payments) to members. If merchant lines are allowed to cross our state, they will bring little benefit to Missouri in the way of power or full time jobs. We are basically as the saying goes “cutting off our nose to spite our face”. If these transmission lines were allowed, we would be taking money right out of our local utility companies and Missouri citizens’ hands and putting it in the pockets of few business owners in other states or countries.
 
This is big business and I doubt Grain Belt (Invenergy) will leave any extra money or savings on the table for the residents of Missouri. As mentioned, I’m a commodity trader for one of the largest Grain Companies in Missouri and in the world. Electricity is a commodity that is traded basically like any other commodity in the world. The first thing my company teaches every new commodity trader on the first day of the job is simple……“Always control the freight, then you always have the leverage”. Grain Belt Express (Invenergy) is trying to gain utility status in Missouri, even though they are not a producer or a seller of electricity. Grain Belt would only be the freight haulers. I see no benefit for Missouri or United States in this proposed project. As far as the “jobs created,” I see no long term employment.
 
This project is not the long term solution for our State. People will not be attracted to move or reside in a county with the highest voltage transmission line in the United States. I have asked myself many times if I would want to be part of a legacy that stood by and let the highest voltage transmission line in the history of the United States be erected and forced my neighbors, life-long friends and fellow Missourians to move from their homes and devalue their property so a private company can profit?
 
Please help to protect property rights, utility companies, and workers of Missouri by doing what is within your ability to stop the abuses of eminent domain for merchant transmission companies, and keep agriculture in Missouri for future generations.
 
Respectfully,
Jay O’Bannon
Want to send your own letter to the Governor?  Missouri Rep. Jim Hansen is collecting them and promises to hand-deliver your letters to the Governor. 

Send yours here:

Rep. Hansen’s e-mail address:[email protected]
Mailing address: State Capitol, 201 W. Capitol Ave., Room 111, Jefferson City, MO 65101-6806
0 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.